BIM Level of Development (LOD): Technical Reference for Scan to BIM Scoping

BIM level of development LOD 100 to 500 illustrated on a building model

This reference summarizes how Level of Development is defined, how each level is used, and how to specify it on a Scan to BIM project.

Definitions

Standards

Document Role
AIA E202-2008 First set out five levels: 100, 200, 300, 400, 500
AIA G202-2013 Project BIM Protocol Form that defines the core levels
BIMForum LOD Specification Adds LOD 350 and expands each level element by element, organized by CSI Uniformat
ISO 19650 series Information-management framework for BIM projects
ISO 7817-1:2024 Level of information need: geometrical information, alphanumerical information, documentation

Level summary

Level Name Reliable for Not reliable for
100 Conceptual Design Massing, early area and volume studies Measurement, coordination
200 Schematic Design Schematic coordination, rough quantity take-off Exact dimensions
300 Detailed Design General coordination, accurate quantity take-off Fabrication
350 Construction Coordination Multi-trade coordination, installation layout Shop fabrication
400 Fabrication and Assembly Shop drawings, bills of materials, spooling n/a
500 As-Built Field-verified record for facility management n/a

LOD 300 versus LOD 350

LOD 300 defines an element on its own. LOD 350 also defines how it connects to everything around it. An LOD 300 pipe has the correct size and route. The same pipe at LOD 350 also shows its hangers, supports and ties into nearby ducts.

Procedure: choosing LOD for a scanned building

  1. List each element group and the decision it must support: coordination, quantity take-off, fabrication or facility handover.
  2. Assign a target level per element, not per project.
  3. Check scan coverage, point density, visibility and the agreed tolerance against each target.
  4. Where the scan cannot support the target, choose supplementary measurements, a denser rescan or a lower level.
  5. Record the result in the LOD matrix of the BIM Execution Plan. When modeling is outsourced, the same list becomes the provider's scope of work.

Procedure: modeling LOD in Revit

  1. Develop and track the element with the system family, loadable family or fabrication part that carries the required geometry and information. If the BIM Execution Plan tracks LOD by parameter, add LOD as a shared parameter.
  2. Set the view's Detail Level (Coarse, Medium or Fine) for display only. It does not change the recorded LOD.
  3. Verify measurable geometry, information, interfaces and source accuracy against the LOD matrix, and stop at the agreed level.

Scan constraints

A registered terrestrial scan can support LOD 300 or higher where coverage, point density, visibility and tolerance are sufficient. Handheld and mobile scanners such as the Leica BLK2GO capture a sparser point cloud and cannot guarantee LOD 300 for every element. A Scan to BIM model is not automatically LOD 500, because a scan records only visible surfaces.

Tolerance options

Where a client sets a tolerance, typical values are 2 in (50 mm), 1.2 in (30 mm), 0.6 in (15 mm) or a custom value. Tighter tolerances add checking time and raise price.